Which metric is the difference between BCWP and BCWS?

Cost Performance Index

Schedule Variance

In earned value management, BCWP is the value of work actually completed, and BCWS is the value of work that was planned to be completed by this point, both based on budgeted cost. The difference between them is Schedule Variance, calculated as Schedule Variance = BCWP − BCWS. A positive variance means you’ve earned more value than was planned (ahead of schedule), while a negative variance means you’re behind.

For context, other metrics use different formulas: Cost Variance is BCWP − AC (earned value minus actual cost), CPI is EV/AC, and SPI is EV/PV. But the specific difference between BCWP and BCWS is Schedule Variance.

Schedule Performance Index

Cost Variance

Want more questions?

All options are one-time payments.

$25.99

30 day premium pass

All the basics to get you started

  • Ad-free experience
  • View your previous attempt history
  • Mobile app access
  • In-depth explanations
  • 30 day premium pass access
$59.99 $171.99 usd

6 month DELUXE pass (most popular)

Everything with the 30 day premium pass FOR 6 MONTHS! & the ultimate digital PDF study guide (BONUS)

  • Everything included in the premium pass
  • $171.99 usd value for $59.99! You save $106!
  • + Access to the ultimate digital PDF study guide
  • + 6 months of premium pass access
  • + Priority support
$15.99 $24.99

Ultimate digital PDF study guide

For those that prefer a more traditional form of learning

  • Available for instant download
  • Available offline
  • Hundreds of practice multiple choice questions
  • Comprehensive content
  • Detailed explanations
Image Description
Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy